August 18, 2017:  Police Station.

August 18, 2017:  Fire station.

August 18, 2017:  Restrooms are roughed in.

August 22, 2017:  Installing the radiant floor heat for the fire station.

 

August 18, 2017:  Continuing the police station block wall.

August 18, 2017:  Continuing the police station block wall.

August 18, 2017:  Preparing the fire station floor for radiant heat and concrete.

August 15, 2017:  Keeping all of the electric organized!

August 15, 2017:  Setting steel.

August 15, 2017:  Laying block for the police station walls.

August 8, 2017:  Setting concrete for fire station floor drains.

August 8, 2017:  Steel frame is being erected.

August 7, 2017:  Steel frame is being erected.

August 1, 2017:  Pouring the fire station floors.

August 1, 2017:  Pouring the fire station floors.

July 25, 2017:  Pouring concrete footers in the police station.

 

July 25, 2017:  Preparing to pour floor slabs in the police station portion of the building.

 

July 25, 2017:  C.S. Davidson testing concrete samples.

 

June 21, 2017:  Electrical conduit is being installed!

June 21, 2017:  Piers are ready for steel!

June 21, 2017:  FIre Station Foundation is done!

June 9, 2017:  Walls are being constructed!

June 9, 2017:  Footers are in place!

June 9, 2017:  New utility poles are being set (so the fire engines can get in and out under the wires!).

June 1, 2017:  Digging out the stormwater basins.

June 1, 2017: Preparing for footers.

June 1, 2017: Compacting the sanitary sewer trenches with a remote compactor.

May 23, 2017: Installing the sewer pipes and preparing footers.

May 16, 2017:  Panoramic view from the furure Board of Supervisors meeting room.

May 16, 2017:  Moving more dirt!

May 10, 2017: Compacting the slab base.

May 9, 2017:  Making progress now that it has been dry for a couple of days!

 

May 8, 2017:  Continuing to prepare the building slab base.

 

May 5, 2017:  Not much happening today, other than rain!!

 

May 4, 2017:  Preparing the base for the building slab!

 

April 27, 2017: Excavating Continues!

April 26, 2017: Project Trailer Has Arrived!

April 24, 2017: Removal of Topsoil (Photo: WHFR)

April 21, 2017:  Groundbreaking (Photo: Buchart Horn)

Left to Right:  Mark Pugliese (Police Chief), Andrew Stern (Township Manager), Kent Gardenr (Supervisor), Frank Burkhart (Supervisor), Dave Dumeyer (Chairman - Supervisors), Jason Sauder (Deputy FIre Chief), John Leas (President - WHFR), Kirk Ament (Trustee - WHFR)