July 9, 2018: Signs are going up! Moving in SOON!
June 12, 2018: Setting the sanitary sewer pipe using horizontal directional boring!
June 12, 2018: Setting the sanitary sewer pipe using horizontal directional boring!
June 8, 2018: Offices are getting final touches!
June 8, 2018: Lunch room has cabinets now!
April 12, 2018: Getting ready to reduce bottled water usage!
April 11, 2018: Corridor floors are under way!
April 11, 2018: Flooring is in. Ceiling Grid is ready for tiles!
April 11, 2018: Somewhere we hope our residents will not ever need to visit!
April 11, 2018: Front doors are in!
February 5, 2018: Police Station hallway is painted!
February 5, 2018: Fire Station hallway drywall is up!
February 5, 2018: Fire Station apparatus bay is starting to get finishing touches!!
January 16, 2018: Painting fire station walls!
January 16, 2018: Hanging drywall!
January 16, 2018: Hanging drywall!
January 16, 2018: Hanging drywall!
December 22, 2017: Running many miles of wire!
December 22, 2017: Interior is now heated!
December 22, 2017: FInal roof section underway!
December 22, 2017: Locker showers have arrived!
December 11, 2017: Aerials of new building from Liberty Belle Drones.
December 11, 2017: Aerials of new building from Liberty Belle Drones.
December 11, 2017: Aerials of new building from Liberty Belle Drones.
December 11, 2017: Aerials of new building from Liberty Belle Drones.
December 11, 2017: Aerials of new building from Liberty Belle Drones.
December 6, 2017: Backside of Fire Station.
December 5, 2017: Community Room South Facing View.
December 5, 2017: Fire Station Doors.
December 5, 2017: Fire Station Bunk Room.
Novemebr 6, 2017: Interior wall framing continues.
Novemebr 6, 2017: Walls are bing insulated.
October 18. 2017: Interior walls are being set.
October 18. 2017: Brick is going up!
September 26, 2017: Curbs are going in.
September 26, 2017: Metal stud walls are going up.
September 20, 2017: Aerial (courtesy Liberty Belle Drone Imaging Services).
September 20, 2017: Aerial (courtesy Liberty Belle Drone Imaging Services).
September 19, 2017: Hanging HVAC Ductwork in the Admin Portion of the Building.
September 19, 2017: Community Room / Multipurpose Room.
September 19, 2017: Fire Station (rear).
September 11, 2017: Police Station.
August 18, 2017: Police Station.
August 18, 2017: Fire station.
August 18, 2017: Restrooms are roughed in.
August 22, 2017: Installing the radiant floor heat for the fire station.
August 18, 2017: Continuing the police station block wall.
August 18, 2017: Continuing the police station block wall.
August 18, 2017: Preparing the fire station floor for radiant heat and concrete.
August 15, 2017: Keeping all of the electric organized!
August 15, 2017: Setting steel.
August 15, 2017: Laying block for the police station walls.
August 8, 2017: Setting concrete for fire station floor drains.
August 8, 2017: Steel frame is being erected.
August 7, 2017: Steel frame is being erected.
August 1, 2017: Pouring the fire station floors.
August 1, 2017: Pouring the fire station floors.
July 25, 2017: Pouring concrete footers in the police station.
July 25, 2017: Preparing to pour floor slabs in the police station portion of the building.
July 25, 2017: C.S. Davidson testing concrete samples.
June 21, 2017: Electrical conduit is being installed!
June 21, 2017: Piers are ready for steel!
June 21, 2017: FIre Station Foundation is done!
June 9, 2017: Walls are being constructed!
June 9, 2017: Footers are in place!
June 9, 2017: New utility poles are being set (so the fire engines can get in and out under the wires!).
June 1, 2017: Digging out the stormwater basins.
June 1, 2017: Preparing for footers.
June 1, 2017: Compacting the sanitary sewer trenches with a remote compactor.
May 23, 2017: Installing the sewer pipes and preparing footers.
May 16, 2017: Panoramic view from the furure Board of Supervisors meeting room.
May 16, 2017: Moving more dirt!
May 10, 2017: Compacting the slab base.
May 9, 2017: Making progress now that it has been dry for a couple of days!
May 8, 2017: Continuing to prepare the building slab base.
May 5, 2017: Not much happening today, other than rain!!
May 4, 2017: Preparing the base for the building slab!
April 27, 2017: Excavating Continues!
April 26, 2017: Project Trailer Has Arrived!
April 24, 2017: Removal of Topsoil (Photo: WHFR)
April 21, 2017: Groundbreaking (Photo: Buchart Horn)
Left to Right: Mark Pugliese (Police Chief), Andrew Stern (Township Manager), Kent Gardenr (Supervisor), Frank Burkhart (Supervisor), Dave Dumeyer (Chairman - Supervisors), Jason Sauder (Deputy FIre Chief), John Leas (President - WHFR), Kirk Ament (Trustee - WHFR)